 | French Family Center Timeline for Construction Please note any/all anticipated dates are subject to change.


- Removal of St. Angela Hall, Maintenance offices, Living Materials Center COMPLETED

- Removal of St. Angela Hall, Maintenance offices, Living Materials Center COMPLETED
- Installation of temporary classrooms COMPLETED

- Removal of Brescia Hall and Merici Hall COMPLETED
- Obtain certificate of occupancy for temporary classrooms COMPLETED
- Completion of new fire lane for French Family Center
- August 15 - Staff move-in to temporary classrooms COMPLETED

- Removal of Brescia Hall and Merici Hall (continued) COMPLETED

- Construct foundation and floor slabs for French Family Center COMPLETED

- Begin floor slabs for north building COMPLETED
- Begin exterior finishes for north building
- Begin concrete panels for south building
- Begin steel erection for south building
- Begin window installation for north building COMPLETED
- Complete floor slabs for south building
- Complete steel erection for south building
- Begin exterior finishes for south building
- Complete window installation for north building COMPLETED
- Begin interior finishes for north building
- Begin exterior finishes for south building

- Continue interior finishes for north building COMPLETED
- Begin window installation for south building

- Begin interior finishes for south building COMPLETED
- Begin landscaping for French Family Center
- New painting, carpet throughout existing facilities

- Final inspections for French Family Center COMPLETED
- New paint, carpet throughout existing facilities

- Receive certificate of occupancy for French Family Center COMPLETED
- Complete pre-occupancy LEED requirements
- Staff move-in to French Family Center
|
|  | |  |
|